|
Web Site Updated 2/8 |
|
|
|
|
|
Painting Begins

Murphy Painting begins the
ceiling this morning

At least we have a black roof on
something
2/8-Murphy Painting began spraying
the ceiling this morning in the new apparatus bays. Work
continues on many areas inside the bays as we move closer to a
future move in date. The boiler arrived and is in process of
being installed. Look for more updates later this week. |
|
 |
|
Thanks Ladies

Construction makes it rough to
find a place to eat

That's all we have to cook with?
2/7-With members staffing the station, some
of "our" ladies got together and made lunch and dinner on
Sunday. Chief 133 actually went to Wegman's for groceries
(believe it, it happened). Once he returned, the task was to
find something to cook with. The ladies brought crock pots and
we moved the gas grill into the kitchen. All in all, with the
social hall cluttered from the construction, we found a place to
sit and eat together. |
|
 |
|
Storm packs some Punch
2/6-7-As the storm rolled
in Friday, members made plans for the weekend. The station was
staffed Friday and Saturday throughout the day and overnight.
Six (6) calls for service were handled, somewhat less than what
we thought, but the fact that it was a weekend with less
traveling made it better. Saturday, crews responded to two gas
leaks, 2 medical assists, and an accident. Sunday, Tanker 33
responded at 01:20 to Carroll Twp, York County for a House Fire.
T33 arrived and staged for about 20 minutes, then released
without service. E133 was alerted for a transfer as a result of
the fire but was canceled when the originally dispatched Engine
responded. |
|
 |
|
Thursday and Friday
Building Update

Crews finish pouring the
remainder of the floor

Last section being pumped in

Brick being removed from the front of the building

Main Electrical Room work

View Looking Down Locust Point Rd

Trust us, it will look better soon!

Apparatus was parked in neighbors driveways again Friday

Friday's work Detail consisted of removing the Engine Bay
Ceiling

Once again, the dumpster got full before we finished the job
2/6-Thursday, the remainder of the
apparatus floor was poured and finished off, including the watch
room. Friday, members began removing the ceiling from the
current apparatus bay. The dumpster was placed inside the bays
in order to make up time to finish before the storm set in. All
of the apparatus was parked in neighbors driveways once again.
Members finished just as the snow was starting to fall. Thanks
to everyone that helped out again. The plan is to finish this on
Thursday, February 11th. |
|
 |
|
January Report
2/3-For the month of
January, the company responded to 60 calls making a quick and
busy start to the month, in fact there were only two days in the
month in which we did not have a call. The busiest call type was
Rescue Calls with 23. Total manpower responding was 633 which
averaged 11 per call. The busiest day of the week was Monday
with 12. The remainder of the report will be added soon. |
|
 |
|
We Have A Floor

Concrete is Pumped into the
Building

The 1st Bay is poured

Looking down from above

Almost half done

Looking really nice

Crews also began demolition on the parapet wall over the old
building

Parapet wall removed
2/3-Rose Hill Concrete got an
early start this morning pouring the 1st half of the apparatus
bay floor. No problems were encountered and the remaining half
will be completed Thursday. APW also completed demolition of the
old parapet wall on the original building. Due to issues with
the concrete block, this had to be removed. A new reinforced
parapet will be added. Also, the fill-in block for the old bays
needs removed and re-laid. All of the brick facade will be
removed this week and replaced with split face to match the new
building. |
|
 |
|
Early Morning Accident
on I81

Single Vehicle impacted the Bus

The morning bus is going to be
late
E2 accessed the wrong direction
from Exit 52 per Chief 7
2/2-Company 33 with R45 and MP45 responded to
I81 in the area of MM53 for a vehicle accident. E233 arrived and
immediately assisted EMS with packaging due to the cold
temperatures. Additional lighting was deployed and used to
provide heat to the victim. Crews checked both vehicles for
hazards and cleaned up debris so the highway could be reopened.
Units cleared around 06:45 |
|
 |
|
Tuesday Building Update

Looking towards Locust Point Rd

A look down from the mezzanine

Looking towards the rear of the
building

Members look at the 2nd floor
2/2-Tuesday evening after the company
meeting, we had the opportunity to take a "look see" at the
progress of the tubing for the heated floor. The entire floor is
ready to go as concrete will be arriving Wednesday morning. We
also took a look around the 2nd floor portion above the live-in
wing. It appears there is plenty of room there for future
growth. |
|
 |
|
Late Afternoon Multi
Injury Accident



1/29-Engine 233 and Traffic 33 responded with
Company 31 and R27 to the 6400 blk of Carlisle Pike at 16:54 for
the accident. Crews arrived and secured both vehicles and
assisted EMS with patient packaging. Once all patients were
accounted for, crews cleaned up debris before going available.
Fire Police had their hands full with the rush hour traffic on
the "Pike". Sq33 and Traffic 33 handled another accident at 9 N
Locust Point Rd just after 18:00. Police requested the units for
debris removal and traffic control at a non injury accident.
Both units cleared before 19:30 |
|
 |
|
RIT to Carlisle on 2nd
Alarm Downtown Job
1/29-Engine 233 (with 4)
responded on the 2nd alarm assignment for the 1st block of N
Hanover St in Carlisle. 1st arriving crews made a great stop on
the fire. E233 set up on side "C" and was released without
incident within 30 minutes. Pictures at
www.effa45.com |
|
 |
|
HVAC Delivery









1/29-In the photos above you see we took
delivery of the new rooftop units for heating, ventilation, and
air conditioning. All units were set in place on the roofs.
Also, the oldest unit which was used for the social hall has
been removed and is being replaced by newer much more efficient
models. Roofers set the trusses and nailed down the plywood at
the kitchen delivery entrance and vestibule. Work continues in
the apparatus bay getting the coils ready for the in floor heat
system. There is one remaining corner on the rear of the
building which needs the split face block finished and it
appears this will be completed next week. Stay tuned for more
photos next week. |
|
 |
|
Wednesday Building
Update

Plywood Sheeting goes on

Watch room roof looking good

Roof ready for the rolled roofing

Look at the main bunk room

Laundry Room

One of the bath rooms

Framing in the Kitchen extension

Stair Tower at rear of the
Building
1/28-Today, work continues around
the fire station. The front roof is now ready for rolled roofing
and then the standing seam metal roof. Interior framing is
moving right along with the live-in area and bunk rooms
completed. The framing has started in the kitchen expansion as
well. Split face work continues around the rear of the building
and the framing for the roof at the rear is also starting.
Tuckey is working on preparing to laying the tubing for the
Engine Bay in floor heat system. The bay floor will be poured
next week. |
|
 |
|
Engine 2 Back in Full
Service

1/27-Engine 2 was out of service Monday and
Tuesday for upgrades to the Amkus Rescue System at Fire & Rescue
Services. All 4 hydraulic hose lines were replaced both on the
reels and from the system to the reels. This required the hose
loads on the rear hose bed to be removed. Tuesday evening after
the fire alarm, members repacked the hose lays. |
|
 |
|
AFA Turns into HVAC
Problem

E133 ready to reverse lay if
needed from E31

Side A of the Building
1/27-Companies 31 and 33 were sent to 1700
Bent Creek Bv for the Fire Alarm at 18:17. E31 arrived and
discovered a light smoke condition on the 2nd floor. The
remainder of apparatus from both companies responded to provide
additional manpower. After a lengthy investigation, crews were
able to trace the problem to an HVAC unit on the roof. Units
cleared at 19:20 |
|
 |
|
Landing Zone at CV High
School

1/27-Engine 233 established at Landing Zone
at CV High School for Rutger's Coach Greg Schiano who was
visiting the school complex possibly scouting football players.
Engine 2 was on scene about two hours before running to the
"Diner" for lunch. |
|
 |
|
Tuesday Building Update

Lines already buried across the
front
The current generator will be
replaced as part of the project

Temporary Station across the
street

Front roof rafters taking shape
Almost ready for plywood
1/26-Tuesday, the front roof framing began
and CV Services and Detraglia Excavating trenched across the
front of the building for the lines running to the new
generator. While this was taking place, the rigs of "Station 1"
had to be parked in neighbors driveways in order to respond.
Thanks to the Hall's and Witmer's for allowing us to use their
driveways all day. |
|
 |
|
Pump Details


1/25-With the heavy rains overnight, crews
knew it would be just a matter of time. The 1st call for
flooding came in at 12:55 with C33 and U33 responding to the
above basement on Old Stonehouse Rd. Crews pumped about 3ft of
water then assisted the homeowner with hooking up a new sump
pump. While on this call, C133 and Sq33 assisted Co. 31 on
Dewalt Dr with another basement. After clearing, U33 responded
to the 3rd call on Locust Point Rd for another basement
flooding. Its been awhile since the trash pump have been used,
but everything worked fine. For the day, E133 handled a fire
alarm around 02:00 and Sq33 handled a Medical Assist at 15:36. |
|
 |
|
Another Crash

1/23-E233 and R31 responded to Carlisle Pike
and RT114 at 10:11 this morning. Units arrived to find no
injuries and secured the vehicles and fluid spill. E233 cleared
at 10:38 |
|
|
|
Framing Delivered

Rafters for the front and back
roof arrive
The trailer enabled everything to
slide right off

Floor Drains installed in the
bays
1/22-Rafters and lumber arrived Friday
for the roofs and crews finished installing the floor drains. |
|
 |
|
Fatal Accident on I81






1/21-Company 33, R45, and MP45 were
dispatched today at 13:40 to a vehicle accident with entrapment
on I81 NB ita of MM53. Chief 7 arrived to find heavy entrapment
of the single occupant of a heavily damaged full size van. Crew
from both Companies worked side by side on the extrication while
EMS crews worked to keep the man alive. Extrication was
completed 24 minutes after arrival. Despite the best efforts of
all personnel, the male passed away while enroute to the
hospital. PSP and the Coroner will be investigating, but intial
reports indicated the van crossed the medial strip from the
southbound lanes and struck a tractor trailer traveling
northbound. The impact caused the entire running gear to be torn
from the trailer. The tractor trailer then jackknifed in the
medial. Units remained on scene for several hours. Traffic was a
nightmare as motorists detoured onto Carlisle Pike. Traffic 33
was the last unit to clear shortly before 17:30. Thanks to E313
(WSBF) for handling the transfer to Station 33. On a side note,
the is the first time we have operated on an extrication with
the "new" Carlisle Fire Rescue Services combined manpower. We
could not have asked for a smoother operation between companies.
Additional information can be found at
www.cumberlink.com |
|
 |
|
Brush 33 gets its first
run of 2010
1/20-At 12:27, Brush and
Tanker 33, MP31 responded to I81 North in the area of MM 55 for
a grass fire. The Brush and Tanker arrived to find a very small
fire caused by a blown steering tire from a tractor trailer. Lt
133 extinguished the fire by "stepping it out". Units cleared at
12:40. |
|
 |
|
Wednesday Update

Concrete is delivered for the
mezzanine Wednesday morning

Concrete is then pumped "up"

Kitchen expansion ready for concrete next

Vestibule entrance also ready for concrete

Rose Hill workers "work" the concrete

Work began reinforcing the steel trusses in the social hall

Metal studs finished in part of the live-in wing

Brick removed from the 3 original bays of the 1956 side of the
building

Split face block complete on 1st 4 bays

2nd four bays half finished
1/20-As you can see above, work
continues around and in the new building. It is nice to see the
split face block complete on part of the apparatus bay door side
of the building and just how the exterior will look with the
columns. |
|
 |
|
Tuesday Morning Update

Split face work around the
apparatus bays

Work progresses on brick removal
around the front of the building

A better view with no plastic on
the upper split face color

Pad poured for new Generator Pad

New entrance at rear of building

Metal stud walls begin to outline
the rooms

Individual room walls laid out
This morning, we were able to get a few
pictures of the exterior work. With the break in the weather
this week so far, Kepler has been making good progress on the
split face work. Interior work this morning shows the walls
beginning to take shape as the metal stud work moves very
quickly. Rose Hill Concrete is making things ready for concrete
delivery on Wednesday for the mezzanine, kitchen, and vestibule
areas. |
|
 |
|
Building Update Monday

Tiny (on right) Shows a worker
where to remove bricks from facade

Metal studs were started in the bunk room area
Shower stalls were delivered
1/18-Pictures today focused on the
work inside the live-in area of the 1st floor. Workers began
installing metal studs and ventilation ducts. Also, on the
outside of the building, workers began removing bricks from the
facade around the windows. These bricks will be used to fill in
the window areas of the current engine bay. |
|
 |
|
Gutting the Kitchen

FF Horn removes the fans, while
Guts works on the cabinets
Appliances disconnected and ready
to move

The Fire Chief making more room
in the Roll Off Dumpster

We're done

Floor Tiles will be removed soon
1/18-Members met Monday to finish gutting the
kitchen so it is ready for renovations. A few of the ladies and
kids worked Saturday morning removing all of the smaller and
packed items. This made our job easier due to only the heavy
stuff needing done Monday. All of the kitchen equipment was
removed (even the sink this time) as well as ceiling tiles,
insulation, and lights. We finished the job in just a few hours
then headed to Middlesex Diner for lunch. Thanks again to our
members who are making this work possible and enough manpower to
complete the job quickly. |
|
 |
|
Early Morning Mobile
Home Fire


1/17-For the second time in a week, crews
from New Kingstown and Shermans Dale responded to Cherry Ln in
Country Manor for a mobile home fire. Last Sunday, Units found a
stove fire with heavy smoke inside. This morning at 00:21, crew
found a bedroom fire. Even though the fire was out on arrival,
the home once again was charged with smoke. Units operated for
over an hour checking for extension, ventilating, and
investigating the cause. |
|
 |
|
1st View of the Exterior


1/16-With the slightly warmer weather this
week, the masons removed some of the plastic covering the front
of the building. This is the 1st time many have seen the
exterior since the splitface block has been added. With the
front walls now ready, work will begin soon on the pitched roof
section between the two walls. |
|
 |
|
Finished Floor

Looking from the rear bay door
towards the rear of the new building
1/14-The floor was found set up this morning
and workers are already marking the floor as the metal framing
studs will be set on Monday. |
|
 |
|
Wednesday Update

Concrete was run in used
motorized wheel barrows

Floor begins to take shape

Glass Doors lead into current
kitchen

Concrete is dumped into the
motorized wheel barrows
1/13-Crews from Rose Hill Concrete poured the
1st floor concrete today for the proposed live in area. Crew
worked until late running the power trowels to make sure
everything was smooth. |
|
 |
|
Building Update for
Tuesday

Concrete being pumped to the 2nd
Floor

Concrete being floated on the 2nd floor

View of the Mezzanine looking towards the front of the building

Rear Mezzanine

Floor Tile removal in Social Hall

Floor down to Concrete in Social Hall

Masons work on the front wall while enclosed in plastic sheeting
1/12-Work is once again progressing on many
areas around the site. Concrete was delivered and pumped to the
2nd floor area. The crew worked for several hours making sure it
was floated smoothly. Masons finished the split face block near
the current bays and moved along to the front of the building
laying CMU block and following with split face. This area was
enclosed in plastic sheeting due to the cold temperatures. The
1st floor live in area and mezzanine are ready for concrete now
as well. CV Services began working on the new generator pad and
Tuckey has relocated the compressors for the current walk in
freezer and refrigerator. The roof in this area has also been
completed. More pictures to follow on Thursday. |
|
 |
|
Accident on I81


1/9-Crews from Companies 33 and 45 responded
to I81 SB in the area of MM49 for a vehicle accident at 11:28.
Units arrived to find the patient self extricated after striking
a tractor trailer nearly head on. Crews contained fluid leaks
from both vehicles and assisted EMS with patient care. Units
cleared at 12:50 |
|
 |
|
Thank You!
1/8-Thank you to
Cumberland-Goodwill Fire Company for donating their bunk bed
frames from the former Station 40 for use in our bunk room once
completed. |
|
 |
|
Building Update

Split face block is raised to the
enclosed scaffolding

Workers attach plywood to the roof line which will eventually
see the roof flashing

Block work is complete dividing the rooms off the Apparatus Bay

Sprinkler piping work has begun

Crew from Diamond Sprinklers install sprinkler heads
1/7-Work is progressing inside the
apparatus bay this week as we have seen the final wall erected
to enclose the building from the weather. Kepler Masonry has
completed the block walls dividing each room in the apparatus
bay and are working on the split face block near the current
Engine 2 bay door. We have been using a single bay door for
response of 4 rigs for almost two weeks now due to cold weather
hampering their efforts. Diamond Sprinkler is installing the
piping for the sprinkler system in the apparatus bays. Work is
also progressing getting the floor areas ready for concrete. |
|
 |
|
Social Hall Update

Night Shift at Work on the
Ceiling

Ceiling Tiles and Insulation being removed

The last couple pieces of paneling being removed

Jeremy with the skid steer removing block Thursday morning

This certainly made the job easy

Finished product Thursday afternoon

Another view looking towards the back
1/7-After working late Wednesday
night and back at it again Thursday morning the volunteers
finished the social hall work. Wednesday night all of the
ceiling tiles and insulation bats were taken down. With the roll
off dumpster full, everything was stacked in the social hall.
Thursday morning began with loading the new dumpster, removing
the kitchen cabinets, cleaning up the broken block from the old
storage room, and taking down the ceiling grid and lights. CV
Services will be wiring temporary lights on Friday to serve
until renovation work begins. Next week, the trophy case will be
dismantled for storage and tile flooring taken up. Special
thanks to the Shughart Family for donating the use of the skid
steer. |
|
 |
|
Demo Day

08:30 This Morning

Before Work Began

Packing the Trophies

Work Begins

Removing the Flag

Removing the Storage Room

Working at the Cabinets

Almost Down

Work on the Back Walls
1/6-After the company meeting
last night, members removed all of the tables, chairs, and
contents of the storage room making ready for demolition to
begin this morning. A group of members nearly 20 strong began
around 08:30 and worked until late afternoon. The walls have
been striped down to the old "green" block walls, storage room
removed, and began on the ceiling. In fact if we wouldn't have
ran out of room in the roll off dumpster we might have been
further along. A group is working tonight on the ceiling tiles
and insulation. Thursday should bring an end to most all of the
social hall work except the tile floor. We would like to thank
everyone who stayed late after the meeting and worked hard all
day today. In true volunteer fashion, we have managed to save
several thousand dollars by doing this work ourselves. Thanks
also to Barry from CV Services who secured power where needed
today.
|
|
 |
|
Morning Chimney Fire

Chief Hall and FF Eckert on the
Roof

FF Eckert Sweeping the Flue
1/3-E233, T33, and Traffic 33
responded at 06:56 to Willow Mill Park Rd for the Chimney Fire.
Units operated for over one hour to contain, extinguish, and
clean the flue pipe. Crews found a working fire blowing from the
chimney upon arrival. Co. 33 assisted Company 31. Other units on
scene were Citizens, Hampden, and Upper Allen. |
|
 |
|
Quick Start to 2010 with
7 Calls in 2 days
1/3-The Volunteers at New
Kingstown started the new year with the 1st call paging in at
01:31 on January 1st with a medical assist in Middlesex
Township. At 10:34, Engine 233 (with 4)transferred to West Shore
Bureau of Fire Station #2 while they operated on a working fire
in New Cumberland. On the 2nd, E233 and T33 responded at 10:54
into Monroe Township for an odor of smoke in a mobile home at
967 W Trindle Rd. Both units arrived and sent manpower to the
staging area, then assisted reloading 5" hose onto E127 before
clearing at 11:23. At 19:22, Both Engines, Tanker, and Traffic
responded for the chimney fire with extension in Middlesex
Township. Crews investigated and discovered fire between the
concrete flue and stainless liner. Fire was contained and
extinguished with minimal water. Units cleared at 20:48. At
23:49, E233 and Traffic 33 responded to Bernheisel Bridge Rd in
the "narrows" for a vehicle accident. Sq33 covered a medical
assist at 23:57 in Middlesex Township and was canceled shortly
after responding. The final call for this report was at 01:00
for a fire alarm at 6695 Carlisle Pk. E233 investigated a false
activation and cleared 21 minutes later. |
|
 |
|
2010 Events
12/28-Due to our Fire
Station Construction and Renovation Project, the 2010 events
schedule will not be posted until such time as we can confirm
our building and grounds will be ready. This includes the
cancellation of the New Year's Day Pork and Sauerkraut Buffet.
Our construction timeline and parking area will not allow for us
to maintain our normal fundraising schedule. We will begin
interior demolition of the social hall after the January Company
Meeting on the 5th. |
|
 |
|
Not Again

It was Engine 2 this time
12/30-After working to get Engine 2 back
in service from a fuel line gasket failure Monday evening late,
it experienced mechanical issues this morning leaving the
station for a medical call. U33 quickly responded in its place
and the Engineers worked to isolate the problem again. By early
evening the cab was down and back in service again. Total repair
costs under $30.00 for parts and no labor charge once again.
Thanks to the Engineers (Sprague and Moyer) and to FF Souder for
your assistance. |
|
 |
|
Early Morning Accident

Chevy Pickup Struck Utility Pole
at CVHS Entrance
12/30-Company 33 and R31 were
dispatched at 03:49 to Carlisle Pike in the area of CV High
School for an accident. Chief 33 arrived at 03:54 to find a
single vehicle into a pole on the main driveway to the school.
With patients out of the vehicle, C33 held E233 and A72. The
crew from the Engine secured the vehicle while EMS obtained
refusals releasing the vehicle operator to Police custody. Co.
33 cleared at 04:29 |
|
 |
|
Wednesday Building
Update

Last remaining high wall begins
to get laid up

All 8 Bays sealed up so temporary heat can be used

Steel framing for watch room is set

Rear of Building, note several courses of split face block
covered

Center Door is delivery door to kitchen, right door is stair
tower

North Wall looking South from New Public Entrance at Rear of
Building
12/30-Today we took time to show
some exterior shots of the progress on the building. If the
weather cooperates Thursday, the building should be sealed so
interior work can move along on the apparatus bays. With
temporary heaters in place, crews can finish laying block and
get ready to pour additional floors. |
|
 |
|
A Look From Above

Much of the Roofing already in
place

Future Parking behind the building

North face of New Building will eventually see dryvit coating

Last remaining corner to be laid up
12/29-A Special Thank You to Chief
Boyce and D/O Brenneman for bringing Truck 45 to the Station
this morning to get a different look at how the construction is
taking shape. Even though it was quite windy and cold, we
managed to get a couple shots in before the camera froze up. |
|
 |
|
Monday Building Update

Crews began framing the north end
of the building

Kepler Masonry began laying up the interior walls behind the
engine bay

Another view of the rooms taking shape
12/28-Masons and Roofers worked
hard Monday getting the building ready to seal up. Many of the
interior block walls starting taking shape. |
|
 |
|
Christmas Eve Crash


12/24-Company 33 and EMS were dispatched at
16:01 hours Christmas Eve for an accident on Bernheisel Bridge
Rd in Middlesex Twp. E233 and Traffic 33 responded. Chief 7
arrived and reported the patients out of the vehicle. The crew
from E2 assisted EMS and checked the vehicle. ALS was requested
to the scene due to patient conditions. After the Medic
evaluated the patient, a decision was made for aero medical.
E133 was dispatched to Stoney Ridge Park for a landing zone for
Life Lion at 16:35. The crew established the LZ, then assisted
with loading the patient into the helicopter. All units were
available shortly after 17:00. |
|
 |
|
Giving Back to the
Community

The Group at Silver Spring
Elementary
Green Ridge Elementary
12/22-A few members loaded up for our annual
trip to Silver Spring, Green Ridge, and Middlesex Elementary
Schools and Eagle View Middle School to deliver complete holiday
meals. The "hat" was passed at our December Company Meeting and
donations from the membership provided for these meals. This is
something we have done as another tradition of the fire company
and we hope that we were able to provide the families (who
remain anonymous) something good to make their holiday special.
Thank you Secretary Joyce Eberly for heading the committee and
getting all the meals together and to our membership for
supporting this once again |
|
 |
|
We Have A Roof!

Engine Bay Roof Decking in Place

Decking in place over ling in wing and 2nd floor
12/24-Building Work this week
focused on placing the roof decking in preparation for the
rubber roof. Crews actually finished welding the decking this
morning. |
|
 |
|
House Fire in Monroe
Township

Very Little damage from the
exterior


1st floor walls marked from
firefighters doing the search

1st floor kitchen area suffered
high heat damage
12/23-Engine 233 and Tanker 33 responded on
the 1st alarm House Fire on Contempra Dr in Monroe Twp at 10:48.
Chief 27 (Warner) arrived and reported nothing showing at first,
then reported smoke showing after investigation. Reports
indicated that possibly three occupants were unaccounted for.
E233 arrived behind E127 as E223 was laying a supply line. The
crew split entering the garage and front door searching the 1st
and 2nd floors with firefighters from Co. 27, 28, 23, and 25.
All searches were negative and occupants were located in a
neighboring house. Crews encountered thick, acrid smoke and heat
while doing the search, but no fire. After ventilation, the fire
origin was loacted on the 1st floor living room and had burnt
itself out. Crews then performed overhaul to insure no extension
before picking up. Thanks to E136 for handling the transfer to
Station 33 and Engineer Sprague for buying us lunch today after
getting the rig back inservice. |
|
 |
|
2nd Alarm Fire in
Middlesex Township


The Home Suffered Heavy
Damage

The crew from E1, E2, and Utility
12/20-Tanker 33 was dispatched at
10:43 with 1st alarm units to the 300 Blk of Enola Rd in
Middlesex Township for the House Fire. Chief 7 had heavy smoke
visible upon response and struck the 2nd alarm at 10:48 which
added the Engine Company. E133 responded at 10:50, Engine 233 at
10: 58, followed by the Utility and Traffic Unit. Crews
attempted an aggressive attack and then were withdrawn at 11:04
to go heavy duty from Truck 39. Crews were able to re-enter the
structure to perform overhaul and mop up hot spots. Crews from
North Middleton, Shermans Dale, Silver Spring,
Empire-Friendship, Cumberland-Goodwill, Carlisle Barracks, West
Pennsboro, Upper Frankford, and Monroe worked together rotating
to extinguish the fire. Control was marked at 11:50. Company 33
cleared the scene at 14:08 and needed another hour to get the
equipment cleaned and ready for service. Special thanks to West
Shore Bureau of Fire and Penn Twp for covering our 1st due and
West Shore for helping us get cleaned up and ready again. More
pictures to follow. |
 |
|
First Snow Storm Hits

I81 South at Exit 49

The Station Saturday Morning
12/19-The 1st Winter Storm
to hit our area with nearly 10" of Snow. This marked the 1st
time in several years that we have been hit with significant
snow. With the snow brought multiple calls. The station was
staffed from Friday night through Sunday with the bunkroom and
lounge filled overnight. Medical Assist procedures were in
effect Saturday and Sunday on all EMS calls to provide manpower
and assistance to EMS crews. Company 33 responded to one
accident (pictured above), 4 medical assist calls, CO Detector,
and an odor of something burning inside. Thanks to the crews
that made themselves available all weekend. |
|
|
|
|
|
 |
|
Thank You!
12/18-The Officers and
Members would like to take the opportunity to thank everyone
that has supported the fire company over the past year by
attending and supporting the fire company through various fund
raising efforts. As we near the end of 2009, we look back at a
very successful year, despite tough economic times, which we owe
to the support we received from the community which includes the
many businesses around the area. Words cannot express our
gratitude. We are confident that our building expansion and
renovation project will secure the future of our department for
many years to come. This project has been years in the making
and has been able to proceed forward with the support we have
received from you. We wish you the best of holidays and a
prosperous new year and once again.....Thanks! |
|
 |
|
Duty Friday
12/18-Duty Friday had
members spread out Friday morning doing various tasks. First and
foremost, with the kitchen expansion progressing, the
compressors that control the walk-in freezer and refrigerator
need to be relocated to the roof. This means both units will be
shut down for several days.
John Gross & Company (Mechanicsburg) was contacted a
graciously allowed us to store items in their freezer until such
time as we are back up and running. Crews emptied both walk-ins
and transported everything to Gross's. Thank you to Brian Gross
for setting aside some room and helping us once again. Engine
233 (with 4) handled a transfer assignment to Upper Allen (Co.
23) while they operated on a house fire in York County. Engineer
Sprague traveled to Karns and purchased soda to fill the
machines before the storm. Back at the station while the Engine
was out, members worked to clean up across the front of the
station. Our marquee sign that was removed in November, was
placed in the storage shed out of the weather. After the Engine
returned, members enjoyed pizza from the NK Deli. |
|
 |
|
Block Work on Kitchen
Expansion

12/18-While crews work on the steel and get
ready to place roof decking, the block work has shifted to the
rear of station on the expansion area of the kitchen. |
|
 |
|
Supporting Project SHARE
12/17-Utility 33 loaded up
some "left over" items at the station and headed to Project
SHARE in Carlisle. Since our fundraising efforts are now over
for 2009 and nothing planned for the first 6 months of 2010, we
decided to donate several cases of eggs, oranges, and even some
candy left from our recent Santa runs. We feel certain this will
be put to go use in the community. |
|
 |
|
Main Steel Set in Place




12/17-Crews began placing the steel girders
over the apparatus bay area Thursday morning and by days end had
them all in place. This work moved very along very quickly. As
we have said before, what a difference a day makes. |
|
 |
|
Operation Save-A-Life
12/16-Company 33, like most
area fire companies, teams up with
ABC27 to provide free smoke
detectors to area residents. This is the 3rd year that Company
33 has participated in this campaign. NKFC received the first
batch of detectors on Wednesday and are available by calling the
fire station at 766-4033. Thanks to Monroe Fire for delivering
them to our station. As we all celebrate the holidays, please
remember that fires can happen at any time and your first
defense is to have working smoke detectors installed in your
home. |
|
 |
|
Concrete Update


12/15-We managed to get a few shots of the
concrete work Tuesday afternoon as crews were waiting for the
concrete to set up before troweling and finishing. Crews worked
until nearly 20:00 before calling it a day. On Wednesday,
insulated blankets were placed over the concrete. Remaining
concrete work will wait until the building is sealed and able to
be temporarily heated. |
|
 |
|
Crash on Hogestown Road


12/15-At 12:31, Engine 233 and Traffic 33
were on the street again responding to the 400 blk of Hogestown
Rd with Co. 31 and R27 to a vehicle accident with confinement.
Lt 228 was in the area and reported no confinement. Units
arrived and assisted EMS packaging the patient and tended to the
vehicles. Units cleared at 13:08. |
|
 |
|
Tractor Trailer
Overturned

Crews stand by waiting on the
wrecker
12/15-Companies 31 and 33 with R27 were sent
this morning around 08:00 to Silver Spring Rd and Carlisle Pike
for the tractor trailer overturned with entrapment. Local
Coordinator 25 (J. Hall) arrived and found negative entrapment.
R31 and E233 crews checked the vehicle for hazards and confirmed
a load of pallets. E233 cleared shortly after 09:00 and Traffic
33 remained. |
|
 |
|
Steel and Concrete

Rose Hill workers pouring the
rooms behind the apparatus bay

Steel is set in place on the 2
story part of the station



Crews begin laying the split face
block

12/15-Crews are hard at work this
week setting the steel and pouring concrete. |
|
 |
|
RIT to Carlisle Again
12/13-E233 (with 5)
responded on the 2nd alarm assignment to Liberty Av for RIT this
evening. E233 arrived and crew members set up equipment in
staging. Members then did a walk around and threw several ground
ladders. RIT was activated on this call to search for possibly
two adults unaccounted for. Prior to making entry, it was
confirmed that they were not home at the time of the fire and
RIT was deactivated. E123 was requested for the 2nd RIT upon our
deployment. Both crews then stood by without further incident.
E233 was available just prior to 23:00. Pictures at
capitalcityfirephotos.com |
|
 |
|
Icy Sunday

Crews responded to the third
accident of the day above.

E233 and Sq33 crew waits to
cleanup the debris
12/13-Besides the monthly
Breakfast at the Station, the weather also kept us busy. As the
roads turned to a sheet of ice, E233 and Traffic 33 responded to
the 300 block of Sample Bridge Rd for an vehicle overturned.
Apparatus had a delayed response as the roads were so icy we
could only travel at low speeds with the chains down. E233
arrived with a single patient out of the vehicle and provided
medical care. R31 and the Ambulance staged on RT944 due to road
conditions. E233 remained on scene nearly an hour waiting for
the wrecker and road crews. Not long after returning to the
station, both units were on the street again to Wertzville Rd
and Sample Bridge Rd for another accident. E233 was canceled
upon arrival and Traffic 33 remained for the duration. At 11:55,
E233, Sq33, and Traffic 33 responded to South Middlesex Rd for
an accident with ejection. Both units had full crews. Chief 7
arrived to find a possible Class 4 patient. E233 and Sq33
arrived with crew members splitting to provide fluid control,
secure vehicles, and confirm a class 4 patient. Units remained
until after 14:00 assisting and cleaning up the massive amount
of debris. Thanks not only to our members for covering the calls
but for making sure the breakfast went off without a hitch and
making sure everything got cleaned up. |
|
 |
|
Saturday Santa

12/12-Company 33 members spent a nice
Saturday on the streets with Santa in our Community. Crew
members passed out oranges and candy to kids and adults. Thanks
to everyone that came out to meet us and we appreciated the
donations that many of you made to us. Crews were on the street
from 08:30 until 16:00, then met up at Hoss's for the evening
meal. Thanks also to E136 (Mt. Holly) for covering the station. |
|
 |
|
RIT to Carlisle

The Fire was next to the former
Station 42

Lt Gutshall and Chief Hall work
to remove the window frame to 3rd floor.
12/12-E233 responded on the RIT
dispatch to Carlisle around 02:30 this morning. The crew set up
multiple ladders to all floors on Sides A, B, and C. The crew
stood by for RIT services then and fortunately were not needed. E2
was available and in quarters just prior to 06:00. |
|
 |
|
Here Comes Santa Claus
12/2-The Fire Company once
again has been chosen to assist Santa with his annual
pre-Christmas visit to the community to check up on kids and
adults alike. Santa will visit from atop the Engines of the New
Kingstown Fire Company while members hand out a special treat to
everyone. This year, Santa will visit on Saturday, December 12th
beginning at 08:30. Please click HERE
for our schedule for the day. Parents are asked to have their
children out to see Santa and receive our treat. Santa's arrival
will be announced by sirens from the Fire Trucks. |
|
 |
|
Breakfast on Sunday
12/7-The monthly Breakfast
Buffet will be held on Sunday, December 13th at 6AM. Santa Claus
will be on hand to greet everyone beginning at 7AM. This will be
our normal breakfast buffet with all of your favorites. Due to
construction and renovations of the social hall, this will be
our last breakfast until quite possibly June 2010. Come out and
support us once again! |
|
 |
|
Meat Raffle Meal
Announced
12/7-The meal for Friday's
meat raffle will be buffet style once again. Baked Ham, Baked
Fish, Mashed Potatoes, and Hot Vegetable will be available free
to all players. Due to construction and renovations, this will
be the last raffle until Fall 2010. Doors open at 5:30 PM. |
|
 |
|
Power Outage Causes
Multiple Calls
12/10-Company 33 responded
to two fire alarms to back to back fire alarms around 19:00
Thursday evening. Units were dispatched to 14 Tiffany Dr, then
Cumberland Valley High School. At 19:48, Fire Police were
requested at Kost Rd, Roadway Dr, I81, Country Club Rd, North
and South Middlesex Rd due to signals out from the power outage.
Traffic 33, Utility 33, and the Squad assisted until power was
restored around 20:45. Thanks to those who responded and
assisted keeping those traveling through our area safe. |
|
 |
|
Thursday Building Update

Steel I-Beams placed to support
front wall
Crane is positioned to begin
setting steel

Steel Beams being set against
present building

Girders waiting for the main roof


12/10-Crews moved in Thursday and began the
task of erecting the steel structure of the building. Steel is
to be completed December 18th and the building under roof. |
|
 |
|
Crew Receives Award for
Cardiac Arrest

12/9-This evening, a group from Silver Spring
Ambulance, Silver Spring Police Department, and New Kingstown
Fire Company received an award from the Emergency Health
Services Federation for successful resuscitation efforts of a
township resident on June 10, 2009. All responders received a
pin and certificate at the presentation held at Company 72's
Quarters. |
|
 |
|
More Steel Arrives

80' Steel Trusses Arrive from New
York

2nd Truck Arrives
Steel is unloaded

New Water Line is installed
12/7-This afternoon, the remainder
of the steel was delivered to the site and E K Services finished
the water line installation under Locust Point Rd |
|
 |
|
Steel and Split Face
Block Arrive

Roof Decking is unloaded

1st load of split face block is
unloaded

1st Load of Steel delivered by Ritner Steel

Crews prepare to cut the new water line across LPR

Crews lay block for the watch room

Front wall work from Monday

Sign this guy up for roof work!

Crews lay up the stair tower
12/7-Monday, the block layers
worked on the front walls facing Locust Point Rd. Concrete work
has been delayed until later this week. Steel delivery began
Tuesday morning, with several trucks parked on Locust Point Rd
waiting to be unloaded.
|
|
 |
|
Friday Building Update

Yesterday, the final piers were
poured for roof overhangs at vestibule and kitchen

Tubing for heated floors begins to take shape

Wall over bay doors is finished off

Outside view of bay door area

North wall at full height

Crews pressure test the in floor heat tubing

Storage room floors ready to pout

Mezzanine wall above shop and tool room

Looking across bay floor towards rooms at back of bays

8 bays in Row
12/4-The Project continues to move
forward as another week is completed. Masons made a lot of
progress on the block work finishing across all 8 bays and
around the rear of the station. The floors under the mezzanine
is now ready to pour and will be done beginning Monday morning.
|
|
 |
|
2010 Officers Elected
12/2-At the regular company
meeting held Tuesday, December 1st, the membership held its
annual election of officers to guide and serve the fire company
for 2010. The following were elected:
President-James Hall
Vice President-Don Baughman
Secretary-Joyce Eberly
Membership Secretary-Heather Hall
Treasurer-Gretchen Horning
Assistant Treasurer-Arla Neitz
Director-James Hall
Director-Barry Horn, Jr
Engineer-Darryl Sprague
Assistant Engineer-Jeremy Moyer
Fire Chief-Curtis Hall
1st Lieutenant-Michael Gutshall
Fire Police Lieutenant-Roger Wagner
*remaining fire line officers will remain the same as 2009 due
to a tiered election process. 3rd Lieutenant (appointed
position) will be announced after the 1st of the year. |
|
 |
|
Silver Spring Township
Tree Lighting
12/2-Wednesday Night is the
annual Holiday Tree Lighting ceremony at the Silver Spring
Township Municipal Complex. The New Kingstown Fire Company has
been invited to participate this year. The event is sponsored by
the Township Parks & Recreation Department, Silver Spring
Community Fire Company, and the Girl Scouts. The event begins at
6:30pm with the arrival of Santa Claus, Tree Lighting, and
Caroling. At 6:45 there will be an ice sculpting. The Central PA
Blood Bank will be on hand until 7PM for those interested in
donating blood. Other events during the evening will be: Little
Elves Crafts for Kids, Free Holiday Treats, Cocoa, and Coffee,
and an opportunity to visit with Santa. Please bring non
perishable canned goods to donate to the New Hope Ministries. We
hope to see you there! |
|
 |
|
Crash on I81


12/1-Engine 233, MP45, R40, Traffic 33, and Traffic 3 responded
to the above accident on I81 near M50 in Middlesex Township at
20:49 tonight. Units arrived to find a single patient out of the
vehicle. Crews secured the vehicle before clearing in a short
time. Both Traffic units remained assisting PSP until 21:43.
Earlier in the day, E133 responded to I81 at MM58 at 06:28 for a
car fire with Co. 31 and 30. E133 was placed available before
committing to the Interstate. |
|
 |
|
The Silence is Broken


12/1-After running just one
call since the 27th, Engine 233 and Traffic 33 responded at
23:55 Monday, November 30th to the 200 block of Hempt Rd for a
single vehicle accident with entrapment. Units arrived to find
heavy front end damage with a single patient pinned. Crews
stabilized the vehicle and began extrication efforts. R31
arrived and assisted. Extrication was complete 27 minutes after
arrival. E31 established a landing zone fore Life Lion nearby.
All units cleared the scene just before 01:00. |