|
Web Site Updated 3/8 |
|
|
|
|
|
Morning Run to Lower
Frankford

RIT equipment is set up on Side
"D"

Crews work from the basket of Truck 39 to remove the roof
3/8-E233 responded with 4 for the
RIT assignment for Lower Frankford Twp at 05:52 this morning for
the House Fire. E233 arrived and set up RIT staging on Side "D"
of the structure. Crews attempted an interior attack but were
driven out when the roof collapsed. E233 crew stood by for
several hours while crews worked to extinguish the fire. Our
thoughts and prayers go out to the family and friends of the
victim. E233 was released at 10:24 |
|
 |
|
Monday Building Update

Harrisburg Glass begins
installing the windows in the social hall

Watch room walls are insulated and ready for drywall

Drywall installation begins

Painting is all but finished in the apparatus bay

Murphy's worked all weekend to finish the painting

Doors and Windows are installed in the new vestibule entrance
3/8-Crews are still working hard
getting things finished up in the apparatus bay. Murphy's worked
all day Saturday to get the paint applied to the apparatus bay;
only a few small areas need finished up. The exterior of the
building was power washed on Saturday and Sunday. Doors are
installed in the vestibule and the metal doors are in place in
the storage rooms in the bay area. Moyer Communications ran the
wiring for the watch room so the drywall crew can get the watch
room finished. The building was bustling all over today as the
nice weather allows work to move along. |
|
 |
|
Snow Melts, Grass Fires
Start
3/6-Brush and Tanker 33
responded at 13:53 to I81 at MM50 for a grass fire in the
median. Units arrived to find a 200' strip on fire and put the
booster line into service. It appeared the fire was caused by a
discarded cigarette. Residents and those traveling through the
area are reminded to use caution, even though we had a good snow
pack, conditions are very dry the next several weeks before
things begin to "green" up. |
|
 |
|
Back to Back Crashes on
the "Pike"

Crew members from E233 secure the
vehicles
3/5-The 3rd ad 4th calls on Friday
were back to back accidents on the Carlisle Pike. E233 responded
at 17:28 to the 6400 block of Carlisle Pike for an unknown
injury accident with Co. 31. E233 was canceled enroute at 17:34.
As members were leaving the station, an accident was heard at
Locust Point Rd and Carlisle Pike. Members loaded the Engine
just as the tones were being dropped for an unknown injury
accident. E233 arrived quickly with the road blocked and a
patient on the roadway. Members immediately took patient care
and made an assessment requesting additional ambulances, a Medic
Unit, and aero medical be placed on standby. Engine and R31
cleared the first crash to respond and provided assistance to
Company 33, then landed the helicopter in the Trinity Church
parking lot. Units remained on scene assisting EMS with multiple
patients before clearing the scene at 18:52. E233, Sq33, and
Traffic 33 responded with a total manpower of 13. For the day,
crews handled four accidents and a brush fire. |
|
 |
|
Friday Building

Glass was installed in the watch
room

Doors begin to get installed in the apparatus bays

Paint is applied to the east wall

Another look at the east wall paint progress

Room with a View

Look at all of the Glass

Another shot of the watch room with the plastic removed
3/4-The highlight of today was the
installation of the glass in the watch room. We have been
waiting for the last section of plastic to be taken off the
building so everyone could see how beautiful the building is
going to be. Paint work is moving along quickly inside the bays
as well. |
|
 |
|
Thursday Building Update

Pennsy delivering another load of
concrete for the kitchen floor

Harrisburg Glass employees working on high windows

Windows and Frames being installed

Verizon arrives with our new Pole

Hand rails are added to the stairs

Ladder for access to the Roof Hatch

Hand Rail on the back stair case in the apparatus bay

Both Hose Dryer Cabinets arrived

Mud applied to the main bunk room

Stair case to 2nd floor area

Looking down the live in hallway

New drains are filled in with concrete in the kitchen

Verizon begins to drill the hole

Pole is set

PPL begins work to ready the pole for electrical service

New transformers will be located soon
3/4-Thursday utility crews arrived
from Verizon and PPL to ready our new service. PPL is co-located
on the Verizon Pole. Due to the location of the water service, a
new pole was set by Verizon, then PPL took over with their part
to get the pole ready to accept the lines and new transformers.
Harrisburg Glass finished all of the windows in the upper
section of the apparatus bays. |
|
 |
|
Pole Fire

3/3-E233 responded to this pole fire in
Leiby's just after clearing the fire prevention program. Units
remained on scene until Verizon arrived to secure their
utilities. |
|
 |
|
Fire Prevention Program
in March

FF Baney Explains the Smoke
Detector

FF Baney and Lt Gutshall demonstrate turnout gear

Lt Gutshall gets close to the kids so they can see the gear
3/3-Fire Prevention programs were
conducted Wednesday and Thursday at a local preschool. Both
days, crews explained our turnout gear and air packs, talked to
the kids about fire safety, and showed the Sesame Street Video.
Thanks to the staff at the preschool for inviting us down and to
the crews both days for taking time to speak to the kids. |
|
 |
|
Looking at the Outside

Bay Door installation complete
and we are seeing the wall pack lights
Windows have been installed on
the rear of the building

New public entrance and
delivery entrance
3/2-With the nice weather this week, we
decided to take a walk around the outside so you could see the
exterior work and what has been accomplished since we have
posted outside shots last. |
|
 |
|
March Off to a Quick
Start
3/2-March started off quick
running 5 calls on Monday. E233 responded at 05:57 to assist
Company 31 with an auto accident on RT114 at I81. The Engine
cleared at 06:27. At 10:30, Sq33 handled a medical assist on
Hathaway Dr. At 14:15, Both Engines and Tanker responded to a
first due truck trailer fire on the PA Turnpike at MM229 WB.
Units arrived to find a working fire in an open top 48' trailer
hauling construction debris. 2 lines were pulled from E133 and
crews accessed using ladders placed against the trailer. After
flowing several thousand gallons, crews declared it under
control, however with the amount and type of materials, we were
unable to fully extinguish the fire. Turnpike authorities would
not allow the trailer to be unloaded so crews broke down. Thanks
to E45 and T31 for the assist. E313 responded on the transfer,
but was canceled enroute. Sq33 handled another medical assist at
16:08 on Cherry Ln. Company 33 and 45 were sent back to the
Turnpike for a rekindle of the truck fire at 17:01. Chief 33
held the response to Company 33. Crews once again flowed more
water into the trailer. Units cleared at 17:47. The trailer was
marked as a controlled burn and left to Turnpike officials. |
|
 |
|
Blast from the Past

3/1-Pictured above is the Old Squad 33 (1970
Dodge) after being purchased, repainted "Tuckey Blue" and
relettered by Tuckey Restoration in Carlisle, PA. The Squad saw
service with Company 33 from 1990-1998. Previously, it ran as
Squad 27 who purchased it new from Swab Wagon Company. Thanks to
M. Snyder for finding the picture. |
|
 |
|
Morning Crash in
Middlesex


2/27-E233 responded with 5 at 08:27 Saturday
morning to S. Middlesex Rd just prior to Old Stonehouse Rd for
an accident. Units arrived to find a single vehicle into a tree
with the operator out of the vehicle. FF Souder came upon the
accident while working and was able to assist with patient care
until the arrival of EMS. Crews secured the vehicle then
assisted EMS packaging the patient. E233 remained until the
vehicle was removed from the scene. Fire Police had the road
closed during the incident. Units were available at 09:03.
Later, at 16:49, E133, T33, and Brush 33 responded with 1st
alarm units to 77 Mountain Ln in Silver Spring Twp for a chimney
fire. Due to tight access, Chief 31 advised units to stage on
Wertzville Rd. Tankers 19 and 20 and R31 made access to the
scene and handled the incident. Staged apparatus cleared at
17:16. |
|
 |
|
It Smells Like Poop!

Crews wait on the pay loader
to move manure to access the fire


Looks like the Deputy has an "enclosed" pump panel
2/26-E133 and T33 responded to
145 Boyer Rd for a manure shed on fire at 07:15 this morning.
E133 arrived 1st in and pulled an attack line to the rear of the
shed where fire had burnt through. The farmer then used a pay
loader to remove the manure from the area which needed soaked
down. All units were clear around 08:30. The high winds added to
the mess causing every scoop of dry manure to blow and stick to
the apparatus and personnel. |
|
 |
|
Friday Building Update

Roof Trusses are reinforced in
the current Engine Bay

New Drain Lines are almost ready in the Kitchen

Painters are making progress on the West Wall

Drywall in place on the mezzanine

A look from above

Painters working on the block filler around the bay doors
2/26-Crews were at it today
despite the high winds. The majority of the work is now
concentrated on the interior portions of the new building and
many areas of the old building. Tuckey is working on HVAC duct
work in the social hall and Stoneberger is working on running
new drain lines to the expanded appliance area of the old
kitchen. The painters continue to work on applying the good coat
of paint to the interior walls and storage rooms. All in all,
everything is coming along fine. |
|
 |
|
Wednesday Building
Update

Windows begin to be installed

All but one door on as of Wednesday morning

Split Face Block completed on the original building

Wall paint begins to take shape in bays

Insulation in the live-in rooms

Main hallway getting drywall

Drywall in main bunk room
2/24-In just 2 days, Baker
Door is making progress with the new bay door installation. The
windows are starting to be installed as well and Drywall crews
began screwing the drywall in place in the live-in wing of the
building. |
|
 |
|
We Have Doors!

Baker Door Employees work on the
first bay

Two panels to go on this one!

Pettibone is loaded with a stack
of man doors
2/22-This afternoon the man doors and bay
doors arrived. Baker Door Company began to install the bay doors
which have glass panels. Not only will this help provide more
light into the apparatus bay area but will also allow our
friends and neighbors in the community to see the equipment
inside. |
|
 |
|
Monday Morning Update on
the Building

Kepler working hard on the front
wall

CMU block is finished and the
split face work begins

CV Services began installing the
lights in the bay this morning

A newer more energy efficient light is being used

The new lights will be equipped with motion sensors

Barrels of Jell await to be injected into the floor heating
system
2/22-As we move closer to
occupying the apparatus bays, crews are working very hard on the
interior. Primer paint coats have been completed and Murphy will
begin applying the actual walls colors this week. Tuckey
continues to work on the boiler, HVAC units, and backup
ventilation system. 55 gallon drums arrived this morning
containing a jell type additive for the in-floor heating system.
Framing inspection was completed this morning as well for all of
the areas containing the metal wall studs clearing the way for
drywall to begin. Kepler finished laying up the front wall on
Friday and began applying the split face block this morning.
Diamond Sprinklers continue to work on piping for the sprinkler
system and the crew from Superior Metal is on site working on
the new hood system. |
|
 |
|
Back to Back Runs on
Saturday Evening


2/20-After three days with no calls,
Companies 33 and 31 were dispatched at 17:07 to the 1st block of
Old Stonehouse Rd for an accident. Chief 131 arrived quickly and
reported a vehicle into a pole with three minor injuries. E233,
Sq33, and Traffic 33 made the response and was assisted by R31.
Crews stabilized the vehicle then assisted EMS with patients.
Fortunately, the pole held phone and tv cable lines and crew
were able to operate directly underneath. While on scene, Engine
and Tanker 33 were dispatched to Allenberry Resort in Monroe Twp
for a furnace fire. E233 responded from the accident, and a
driver was sent to the station for the Tanker. E233 arrived and
staged for just a short time before being placed available. T33
was canceled before response. Co. 33 had 18 personnel turn out. |
|
 |
|
2010 In-House Training
Schedule
2/19-The 2010 NKFC Training
Schedule has been added to the training page. Members, please
note CPR/AED classes the weekend of March 12th. |
|
 |
|
Friday Morning Update

Painting continued this morning
as more black is spraying on the roof

Kepler's crew back at work again setting the new front wall

And it looked so nice with just the plastic
2/19-This morning, the masons
arrived and began laying up the new front wall. With the warmer
temperatures they should be to the roof later today. Provisions
for the split face are in place so they should be following
right along next week if the weather holds. |
|
 |
|
Thursday Update

Early Thursday morning, the front
of the Building Looked like this

45 minutes later it looked like this-front wall is gone

Stairs to the mezzanine were installed

2nd staircase at other end of the bay

New boiler is installed

Diamond Sprinkler makes the connection to the main water line
2/18-A look around the building
yesterday showed a lot of work being performed. First and
foremost, the front wall of the 1955 side of the original
building had to be totally demolished due to issues with the
block rendering it not able to be salvaged. In a matter of just
a few minutes, the wall was gone. Bracing had been placed inside
to old social hall to support the roof. The stairs also arrived
and crews began installing them. The sprinkler system has been
connected to the riser and work continues to get the boiler
ready to go. |
|
 |
|
Wednesday Building
Update

Pad ready to accept the new
generator Wednesday morning

Block filler has been completed on most of the walls

Rooms off the "horseshoe" also have been completed with the
filler

As of Wednesday morning, only one of the high walls needed
sprayed

New 300 kW Diesel Generator is now in place.
2/17-Murphy painting is progressing well
inside the apparatus bay as the block filler is being applied to
the walls. CV Services installed the new generator and is in
process of preparing it for operation. |
|
 |
|
Busy Two Months Get Us
Over 100 Early
2/13-Monroe's Crew running
two calls during the banquet got us over 100 Calls for the year
already. It has been quite busy with calls so far this year and
is probably the earliest in the fire company's history that we
broke 100 in under two months. |
|
 |
|
Annual Company Banquet
2/13-Our annual fire company awards banquet was held on
Saturday, February 13th at the Comfort Suites in Carlisle. Over
170 members and invited guests filled the banquet hall and took
time to relax and recap the past year of the fire company.
Special thanks to the crew from Monroe Fire Company who staffed
E233 while our members took "the night off".
For Pictures Click Here |
|
 |
|
Another Snowstorm

2/10-Once again, the station was well staffed
throughout the most recent blizzard, even though many over our
calls were during daylight hours. In the two day period, crews
responded to 8 medical assists, 1 fire police deployment, 1 fire
alarm, 1 structure fire, and 1 vehicle accident. Thanks to
everyone once again for getting the rigs on the street. |
|
 |
|
AFA Turns Into Working
Fire



2/10-At 08:39 in the middle of the blizzard,
Companies 31 and 33 were dispatched to a fire alarm on Bent
Creek Blvd. E31 arrived, gained access using the Knox Key and
began investigating. A smoke condition was encountered on the
2nd floor. Command then upgraded the box to a structure
assignment which added the 2nd Engine and Tanker from 33, Rescue
and Tanker 31, Hampden, Citizens, Washington, and Truck 45 (CFRS).
E133 arrived and took the rear of the building and sent its crew
inside to assist E31. Units were able to locate the fire in the
ceiling in several rooms on the 2nd floor. High rise packs and
leader lines were deployed from E31. E330 laid in from a hydrant
to supply Truck 30 which also located fire behind the parapet at
the roof near HVAC units. E233 picked up the hydrant to supply
E330. T33 hooked to E31 to supply if needed. Crews were able to
control the fire quickly and begin salvage operations. The
investigation revealed part of the flat roof structure had
failed causing a rigid gas line connection to an HVAC to fail
and feed the gas fire. Crews functioned well together despite
the high winds and blinding snow throughout the incident. |
|
 |
|
Adopt A Hydrant
2/10-With yet another
Winter Storm hitting us hard and as snow is piling up along the
streets, residents and businesses are asked to Adopt A Fire
Hydrant that may be nearby. This will save the fire company
precious time in the event we need to respond to your home or
business. Please take the time and shovel out around the hydrant
so the it is visible and will allow us to make the proper
connections. Most hydrants are equipped with a "marker flag"
enabling us to see them, however taking the extra time to shovel
the hydrant would be much appreciated. |
|
 |
|
Painting Begins

Murphy Painting begins the
ceiling this morning

At least we have a black roof on
something
2/8-Murphy Painting began spraying
the ceiling this morning in the new apparatus bays. Work
continues on many areas inside the bays as we move closer to a
future move in date. The boiler arrived and is in process of
being installed. Look for more updates later this week. |
|
 |
|
Thanks Ladies

Construction makes it rough to
find a place to eat

That's all we have to cook with?
2/7-With members staffing the station, some
of "our" ladies got together and made lunch and dinner on
Saturday. Chief 133 actually went to Wegman's for groceries
(believe it, it happened). Once he returned, the task was to
find something to cook with. The ladies brought crock pots and
we moved the gas grill into the kitchen. All in all, with the
social hall cluttered from the construction, we found a place to
sit and eat together. |
|
 |
|
Storm packs some Punch
2/6-7-As the storm rolled
in Friday, members made plans for the weekend. The station was
staffed Friday and Saturday throughout the day and overnight.
Six (6) calls for service were handled, somewhat less than what
we thought, but the fact that it was a weekend with less
traveling made it better. Saturday, crews responded to two gas
leaks, 2 medical assists, and an accident. Sunday, Tanker 33
responded at 01:20 to Carroll Twp, York County for a House Fire.
T33 arrived and staged for about 20 minutes, then released
without service. E133 was alerted for a transfer as a result of
the fire but was canceled when the originally dispatched Engine
responded. |
|
 |
|
Thursday and Friday
Building Update

Crews finish pouring the
remainder of the floor

Last section being pumped in

Brick being removed from the front of the building

Main Electrical Room work

View Looking Down Locust Point Rd

Trust us, it will look better soon!

Apparatus was parked in neighbors driveways again Friday

Friday's work Detail consisted of removing the Engine Bay
Ceiling

Once again, the dumpster got full before we finished the job
2/6-Thursday, the remainder of the
apparatus floor was poured and finished off, including the watch
room. Friday, members began removing the ceiling from the
current apparatus bay. The dumpster was placed inside the bays
in order to make up time to finish before the storm set in. All
of the apparatus was parked in neighbors driveways once again.
Members finished just as the snow was starting to fall. Thanks
to everyone that helped out again. The plan is to finish this on
Thursday, February 11th. |
|
 |
|
January Report
2/3-For the month of
January, the company responded to 60 calls making a quick and
busy start to the month, in fact there were only two days in the
month in which we did not have a call. The busiest call type was
Rescue Calls with 23. Total manpower responding was 633 which
averaged 11 per call. The busiest day of the week was Monday
with 12. The remainder of the report will be added soon. |
|
 |
|
We Have A Floor

Concrete is Pumped into the
Building

The 1st Bay is poured

Looking down from above

Almost half done

Looking really nice

Crews also began demolition on the parapet wall over the old
building

Parapet wall removed
2/3-Rose Hill Concrete got an
early start this morning pouring the 1st half of the apparatus
bay floor. No problems were encountered and the remaining half
will be completed Thursday. APW also completed demolition of the
old parapet wall on the original building. Due to issues with
the concrete block, this had to be removed. A new reinforced
parapet will be added. Also, the fill-in block for the old bays
needs removed and re-laid. All of the brick facade will be
removed this week and replaced with split face to match the new
building. |
|
 |
|
Early Morning Accident
on I81

Single Vehicle impacted the Bus

The morning bus is going to be
late
E2 accessed the wrong direction
from Exit 52 per Chief 7
2/2-Company 33 with R45 and MP45 responded to
I81 in the area of MM53 for a vehicle accident. E233 arrived and
immediately assisted EMS with packaging due to the cold
temperatures. Additional lighting was deployed and used to
provide heat to the victim. Crews checked both vehicles for
hazards and cleaned up debris so the highway could be reopened.
Units cleared around 06:45 |
|
 |
|
Tuesday Building Update

Looking towards Locust Point Rd

A look down from the mezzanine

Looking towards the rear of the
building

Members look at the 2nd floor
2/2-Tuesday evening after the company
meeting, we had the opportunity to take a "look see" at the
progress of the tubing for the heated floor. The entire floor is
ready to go as concrete will be arriving Wednesday morning. We
also took a look around the 2nd floor portion above the live-in
wing. It appears there is plenty of room there for future
growth. |
|
|
|
 |