Weeks 6 & 7 Updates! |
By Lieutenant Alexander Hall | |
December 1, 2023 | |
Lots of progress this week. Stair platforms were delivered and installed. Plumbing and drainage was inspected. Drywall and insulation was delivered Thursday and was already being installed. Special thanks to Andy Souder for the use of his equipment and Gerald Steigleman for his assistance in moving the drywall for the construction crews! |
|